(5) Remove clutch piston from clutch retainer.

Remove piston by rotating it up and out of retainer.

(6) Remove seals from clutch retainer piston bore

and clutch retainer hub. Discard both seals as they
are not reusable.

CLEANING

Clean the servo piston components (Fig. 109) with

solvent and dry them with compressed air.

Fig. 107 Front Clutch Components - Typical

1 - SNAP-RING (WAVE)

7 - SEAL

2 - REACTION PLATE

8 - PISTON

3 - CLUTCH DISC

9 - SPRING

4 - CLUTCH PLATE

10 - SNAP-RING

5 - SEAL

11 - SPRING RETAINER

6 - CLUTCH RETAINER

WG

AUTOMATIC - 44RE

21s - 119

FRONT SERVO (Continued)

2001 JEEP GRAND CHEROKEE

INSPECTION

Inspect the servo components (Fig. 110). Replace

the springs if collapsed, distorted or broken. Replace
the guide, rod and piston if cracked, bent, or worn.
Discard the servo snap-ring if distorted or warped.

Check the servo piston bore for wear. If the bore is

severely scored, or damaged, it will be necessary to
replace the case.

Replace any servo component if doubt exists about

condition. Do not reuse suspect parts.

ASSEMBLY

Clean and inspect front servo components.
(1) Lubricate new o-ring and seal rings with petro-

leum jelly and install them on piston, guide and rod.

(2) Install rod in piston. Install spring and washer

on rod. Compress spring and install snap-ring (Fig.
111).

Fig. 108 Compressing Front Clutch Piston Spring

1 - FRONT CLUTCH SPRING
2 - COMPRESSOR TOOL C-3575-A
3 - RETAINER SNAP-RING
4 - SPRING RETAINER

Fig. 109 Front Servo Piston

1 - PISTON RINGS
2 - O-RING
3 - SNAP-RING
4 - SEAL RING
5 - PISTON ROD GUIDE
6 - SNAP-RING
7 - SERVO SPRING
8 - PISTON ROD
9 - SERVO PISTON

Fig. 110 Front Servo Piston

1 - PISTON RINGS
2 - O-RING
3 - SNAP-RING
4 - SEAL RING
5 - PISTON ROD GUIDE
6 - SNAP-RING
7 - SERVO SPRING
8 - PISTON ROD
9 - SERVO PISTON

21s - 120

AUTOMATIC - 44RE

WG

FRONT SERVO (Continued)

2001 JEEP GRAND CHEROKEE

GEAR SHIFT CABLE

DIAGNOSIS AND TESTING - GEARSHIFT
CABLE

(1) The floor shifter lever and gate positions

should be in alignment with all transmission PARK,
NEUTRAL, and gear detent positions.

(2) Engine starts must be possible with floor shift

lever in PARK or NEUTRAL gate positions only.
Engine starts must not be possible in any other gear
position.

(3) With floor shift lever handle push-button not

depressed and lever in:

(a) PARK position - Apply forward force on cen-

ter of handle and remove pressure. Engine starts
must be possible.

(b) PARK position - Apply rearward force on cen-

ter of handle and remove pressure. Engine starts
must be possible.

(c) NEUTRAL position - Normal position. Engine

starts must be possible.

(d) NEUTRAL position - Engine running and

brakes applied, apply forward force on center of
shift handle. Transmission shall not be able to shift
from NEUTRAL to REVERSE.

REMOVAL

(1) Shift transmission into PARK.
(2) Raise vehicle.

(3) Remove the shift cable eyelet from the trans-

mission manual shift lever (Fig. 112).

(4) Remove shift cable from the cable support

bracket.

(5) Lower vehicle.
(6) Remove necessary console parts for access to

shift lever assembly and shift cable. (Refer to 23 -
BODY/INTERIOR/FLOOR CONSOLE - REMOVAL)

(7) Disconnect cable at shift lever and shifter

assembly bracket (Fig. 113).

(8) Remove the nuts holding the shift cable seal

plate to the floor pan (Fig. 114).

(9) Pull cable through floor panel opening.
(10) Remove shift cable from vehicle.

INSTALLATION

(1) Route cable through hole in floor pan.
(2) Install seal plate to studs in floor pan.
(3) Install nuts to hold seal plate to floor pan.

Tighten nuts to 7 N·m (65 in.lbs.).

(4) Install the shift cable to the shifter assembly

bracket. Push cable into the bracket until secure.

(5) Place the floor shifter lever in PARK position.
(6) Loosen the adjustment screw on the shift cable.
(7) Snap the shift cable onto the shift lever pin.
(8) Raise the vehicle.

Fig. 111 Front Servo

1 - PISTON RINGS
2 - O-RING
3 - SNAP-RING
4 - SEAL RING
5 - PISTON ROD GUIDE
6 - SNAP-RING
7 - SERVO SPRING
8 - PISTON ROD
9 - SERVO PISTON

Fig. 112 Transmission Control Cables & Fluid Lines

1 - TRANSMISSION SHIFTER CABLE
2 - THROTTLE VALVE CABLE
3 - TRANSFER CASE SHIFTER CABLE
4 - TRANSFER CASE SHIFTER CABLE BRACKET RETAINING
BOLT(S)
5 - THROTTLE VALVE CABLE BRACKET RETAINING BOLT
6 - ELECTRICAL CONNECTORS
7 - TRANSMISSION FLUID LINES

WG

AUTOMATIC - 44RE

21s - 121

FRONT SERVO (Continued)

2001 JEEP GRAND CHEROKEE

(9) Install the shift cable to the shift cable support

bracket.

(10) Shift the transmission into PARK. PARK is

the rearmost detent position on the transmission
manual shift lever.

(11) Snap the shift cable onto the transmission

manual shift lever.

(12) Lower vehicle.
(13) Verify that the shift lever is in the PARK posi-

tion.

(14) Tighten the adjustment screw to 7 N·m (65

in.lbs.).

(15) Verify correct shifter operation.
(16) Install any console parts removed for access to

shift lever assembly and shift cable. (Refer to 23 -
BODY/INTERIOR/FLOOR CONSOLE - INSTALLA-
TION)

ADJUSTMENTS - GEARSHIFT CABLE

Check adjustment by starting the engine in PARK

and NEUTRAL. Adjustment is CORRECT if the
engine starts only in these positions. Adjustment is
INCORRECT if the engine starts in one but not both
positions. If the engine starts in any position other
than PARK or NEUTRAL, or if the engine will not

start at all, the park/neutral position switch or TRS
may be faulty.

(1) Shift transmission into PARK.
(2) Remove floor console as necessary for access to

the shift cable adjustment. (Refer to 23 - BODY/IN-
TERIOR/FLOOR CONSOLE - REMOVAL)

(3) Loosen the shift cable adjustment screw (Fig.

115).

(4) Raise vehicle.
(5) Unsnap cable eyelet from transmission shift

lever (Fig. 116).

(6) Verify transmission shift lever is in PARK

detent by moving lever fully rearward. Last rearward
detent is PARK position.

(7) Verify positive engagement of transmission

park lock by attempting to rotate propeller shaft.
Shaft will not rotate when park lock is engaged.

(8) Snap cable eyelet onto transmission shift lever.
(9) Lower vehicle
(10) Tighten the shift cable adjustment screw to 7

N·m (65 in.lbs.).

(11) Verify correct operation.
(12) Install any floor console components removed

for access. (Refer to 23 - BODY/INTERIOR/FLOOR
CONSOLE - INSTALLATION)

Fig. 113 Transmission Control Cables & Fluid Lines

1 - TRANSMISSION SHIFTER CABLE
2 - THROTTLE VALVE CABLE
3 - TRANSFER CASE SHIFTER CABLE
4 - TRANSFER CASE SHIFTER CABLE BRACKET RETAINING
BOLT(S)
5 - THROTTLE VALVE CABLE BRACKET RETAINING BOLT
6 - ELECTRICAL CONNECTORS
7 - TRANSMISSION FLUID LINES

Fig. 114 Transmission Control Cables & Fluid Lines

1 - TRANSMISSION SHIFTER CABLE
2 - THROTTLE VALVE CABLE
3 - TRANSFER CASE SHIFTER CABLE
4 - TRANSFER CASE SHIFTER CABLE BRACKET RETAINING
BOLT(S)
5 - THROTTLE VALVE CABLE BRACKET RETAINING BOLT
6 - ELECTRICAL CONNECTORS
7 - TRANSMISSION FLUID LINES

21s - 122

AUTOMATIC - 44RE

WG

GEAR SHIFT CABLE (Continued)

2001 JEEP GRAND CHEROKEE

 

 

 

 

 

 

 

Content   ..  901  902  903  904   ..